NEW CABLEWAY CONSTRUCTION

GONDOLA GRAND-BRHLISKÁ

in OTUPNÉ resort

 

cableway name: GRAND -  BRHLISKÁ

type: 8-seater GONDOLA GRAND JET / DOPPELMAYR

manufacturer: DOPPELMAYR GmbH - Wolfurt
capacity: 2400 people / hour

down station: 1113 m a.s.l.   top station: 1425 m a.s.l.

difference in altitude: 311,75 m   length: 1959,69 m   velocity: 6 m/s   ride time: 6,47 min.

 

beginning of construction: May 2009     opening: on 19th December 2009

investor:  WEBIS s.r.o.       amount of investment: 13 million €

 

OLD GONDOLA OTUPNÉ

A new cableway will replace the original gondola for four people OTUPNÉ - BRHLISKÁ called also an „egg" (Tatrapoma, 1983), marked as M, which capacity was 1200 people per hour and its sloping length of 1602m.

 

The new gondola :

- twice as big transport capacity

- 358 m longer

- the down station  next to the hotel Grand

- 65 cabins for 8 passenger

- modern design, black frames and orange window panes

- a unique colour combination

NEW GONDOLA OTUPNÉ

The first cabins have arrived at Jasná on 30th Oct.

- cabin weight without load 670 kg

- full inside cabin weight ca 1300 kg

- bottom 2034 mm x 1878 mm

- heigth 4055 mm

- report >

CABIN CABLEWAY LOADING TESTS on 30th November report >

 

Project:

údolná stanica

údolná stanicavýstupná stanica

 

 

 

 

 

 

 

 

 

 

 

A part of the construction project are also:

 

Extension of the ski slope No 10 VRBICKÁ by 890 m and its widening in the upper part

- the ski slope will end at the bottom station of the cableway, in front of the hotel Grand
- as the new ski slope will cross the car road a tunnel for cars has been built
- the resorts Biela Púť and Otupné will be inerconnected in the bottom part of the ski slopes Biela Púť and Vrbická (a new traverse from Biela Púť to Vrbická)

 

NEW PART OF SKI SLOPE Vrbická

- from the traverse No 19 Vrbická and its extending, equipped with snowmaking facility
- it will bypass a difficult part - a steep drop off on the ski slope Vrbická
  (it has been a problem to less experienced skiers)

 

technical parameters of the new ski slope No 10 Vrbická:

start: 1425 m a.s.l.   finish: 1111 m a.s.l.    length: 2570 m

artificial snow: yes     difficulty: easy, blue

 

technical parameters of the new ski slope No 10a Vrbická

start: 1340 m a.s.l.    finish: 1255 m a.s.l.     length: 700 m

artificial snow: yes     difficulty: medium, red

 

technical parameters of the new traverse No 19 Biela púť - Grand:

length: 150 m difference in altitude: 20 m

artificial snow: no       difficulty: easy, blue

 

Construction of a new snow-making facility in the resort Otupné

- along the ski slope a new snowing system comprising 35 snowing canons will be built

- completion of the snow-making facility for the entire ski slope Vrbická

- construction of the snow-making facility for the new part of ski slope

 

foto z eventu


some photos from construction >            news about building >

 

 

The project will be continued, but in the following seasons:)

 

ATTENTION!

WE KINDLY ASK ALL TOURISTS TO AVOID THE LOCALITY OTUPNÉ (SKI SLOPE VRBICKÁ, CABIN CABLE CAR) FOR SAFETY REASONS. IT IS ALSO IMPORTANT TO MAINTAIN THE CONTINUITY OF CONSTRUCTION WORK. THANK YOU FOR YOUR UNDERSTANDING.

new gondola project

 

© 2005-2012 Tatry mountain resorts, a.s.
Tatry mountain resorts, a.s.
Vysoké Tatry - Tatranská Lomnica, Štrbské Pleso, Starý Smokovec
Aquapark TATRALANDIA, Liptovský Mikuláš
Hotel Tri Studničky**** Demänovská Dolina
Hotel Grand**** Jasná, Nízke Tatry
Chalets Jasná de Luxe, Nízke Tatry - Záhradky
Holiday Village Tatralandia
Hotel Srdiečko**, Chopok juh
Grandhotel**** Starý Smokovec
Grandhotel Praha**** Tatranská Lomnica
Hotel FIS*** Štrbské Pleso